CMH: Building Today. Tomorrow. Always.
Our capital campaign will allow for the physical transformation of a 70-year old facility, helping Community Memorial promote quality of patient care and safety, improve efficiencies and cost savings, and improve access to care across the Community Memorial system.
Construction Phase 01
JUNE 1, 2020 - DECEMBER 17, 2020
By August 25, 2020: Temporarily relocate blood draw/bone density
August 25, 2020 - December 17, 2020: Build permanent lab draw facility
September 18, 2020 - December 17, 2020: Set up temporary Emergency Department Waiting Room/Registration
Construction Phase 02
DECEMBER 18, 2020 - SEPTEMBER 24, 2021
By May 18, 2021: Turn over Central Sterile
May 19, 2021 - September 24, 2021: New CT build out
Construction Phase 03
SEPTEMBER 27, 2021 - DECEMBER 29, 2021
Complete medical surgery (North wing) build out
Complete patient wing (South)
Establish temporary rehabilitation department
Complete Nuclear Medicine build out
Begin Radiology Department build
Construction Phase 04
DECEMBER 29, 2021 - JULY 7, 2022
Complete Radiology Department build out