Construction Phase 01

JUNE 1, 2020 - DECEMBER 17, 2020

floor plan for phase 1 of community memorial hospital construction.

By August 25, 2020: Temporarily relocate blood draw/bone density

August 25, 2020 - December 17, 2020: Build permanent lab draw facility

September 18, 2020 - December 17, 2020: Set up temporary Emergency Department Waiting Room/Registration

Construction Phase 02

DECEMBER 18, 2020 - SEPTEMBER 24, 2021

floor plan for phase 2 of community memorial hospital construction.

By May 18, 2021: Turn over Central Sterile

May 19, 2021 - September 24, 2021: New CT build out

Construction Phase 03

SEPTEMBER 27, 2021 - DECEMBER 29, 2021

floor plan for phase 1 of community memorial hospital construction.

Complete medical surgery (North wing) build out

Complete patient wing (South)

Establish temporary rehabilitation department

Complete Nuclear Medicine build out

Begin Radiology Department build

Construction Phase 04

DECEMBER 29, 2021 - JULY 7, 2022

floor plan for phase 2 of community memorial hospital construction.

Complete Radiology Department build out